Ground Improvement Method "Rising W" Construction Procedure
A detailed introduction to the construction process from preparation work to completion for "Rising W"!
Here are the construction procedures for "Rising W." In the preparation work, to ensure stability during the operation and movement of the construction machinery, we will carry out measures such as laying steel plates, surface ground improvement, curing, alignment and marking, inspection and calibration of measuring devices, and checking the condition of the solidifying agents. 【Construction Procedures】 ■1. Preparation Work ■2. Positioning ■3. Start Excavation ■4. Confirm Excavation Depth ■5. Introduce Improved Soil and Solidifying Agent Slurry ■6. Mixing ■7. Repeat ■8. End of Mixing and Construction *For more details, please refer to the PDF document or feel free to contact us.